Friday update 1/15/21

Hello to all, East end AC unit updates are complete! They will start improvements Monday with roof units which will effect 1206, 1010, 810, 610, 410, 1110, 910, 710, 510, and 310. They will still have heat for the 3

Patsy Layfield January 15, 2021January 15, 2021 Updates Read more

Monday Update 1/11/2021

Good morning Regency Isle Homeowners, I have a couple of things to update you on. Estes will not start the units today that I mentioned on Friday. They will start this on Tuesday. They will only shut off the power

Patsy Layfield January 11, 2021January 11, 2021 Updates Read more

Update January 8, 2021

Happy New Year!! We are moving forward with our AC improvements. Estes started the East side AC areas. All AC units should be complete by Wednesday of next week. The units will be put on taller stands to keep them

Patsy Layfield January 8, 2021January 8, 2021 Updates Read more

MERRY CHRISTMAS TO ALL!

On behalf of Frank, Elray, Vanessa, and myself we would like to say thank you for your generosity and support for this past year. I can say it’s been a challenging one for sure. We will continue forward to make

Patsy Layfield December 24, 2020December 24, 2020 Updates Read more

December 18, 2020 Update

Hello everyone! Well Christmas is upon us. I hope next year is a better year. All of the AC units that needed to be replaced have been completed. Island Air will be starting on the eastside line sets sometime next

Patsy Layfield December 18, 2020December 18, 2020 Updates Read more

December 11, 2020 Update

Hi everyone, Frank has finished the walk through with Coastal Construction today. There are a few minor things for them to correct and they have already started that process. So, other than people upgrading their flooring it should all be

Patsy Layfield December 11, 2020December 11, 2020 Updates Read more

DECEMBER 4, 2020 UPDATE

Hello to all, We have made a lot of progress, but just shy of being able to do the FINAL walk through. This will be done next week. We had to have carpet backordered and some of the units are

Patsy Layfield December 4, 2020December 4, 2020 Updates Read more

November 20 Update

Hello to all, Interior Unit Repairs – Frank is working with Coastal going through a unit by unit inspection and identifying punch list items to complete. Chris (Coastal Construction) is now using his local crews to complete this work in

Patsy Layfield November 20, 2020November 20, 2020 Updates Read more

Update 11/17/20

Frank and I just met with Coastal a few minutes ago. They will be starting on 01 and 02 units in the morning to fine tune repair issues we found on Monday. I don’t have an exact time frame for

Patsy Layfield November 17, 2020November 17, 2020 Updates Read more

November 13, 2020 Update

Hello to all, I want to update you all on repairs for Regency Isle. All repairs have been completed. We will be going into each unit on Monday to inspect the work that was done and any issues that need

Patsy Layfield November 13, 2020November 13, 2020 Updates Read more