Hello to all, Interior Unit Repairs – Frank is working with Coastal going through a unit by unit inspection and identifying punch list items to complete. Chris (Coastal Construction) is now using his local crews to complete this work in
Update 11/17/20
Frank and I just met with Coastal a few minutes ago. They will be starting on 01 and 02 units in the morning to fine tune repair issues we found on Monday. I don’t have an exact time frame for
November 13, 2020 Update
Hello to all, I want to update you all on repairs for Regency Isle. All repairs have been completed. We will be going into each unit on Monday to inspect the work that was done and any issues that need
Friday November 6, 2020 Update
Hello to all, Update on units completed are as follows: 901, 904, 801, 1203, 701, & 806. The condenser lines for 11 & 12 stacks will be done by 11/11/20. Otis came out to repair the call buttons for elevators
11/3/20 From Dale Kline, President
Dear Regency Isle Homeowners,The recovery from the impact of Hurricane Sally is proceeding, albeit more slowly than many would like. The RI Staff and the Board is doing whatever it possibly can to get the property back to the best